O-Train Line 1 early closure on Sunday, May 11 for Stage 2 testing
O-Train Line 1 service will end early, at 8 pm, instead of 11 pm on Sunday, May 11. Full Line 1 service will resume Monday, May 12 at 5 am.
During the temporary closure, R1 replacement bus service will run from 8 pm to 11 pm between Tunney’s Pasture and Blair stations. In addition to R1, shuttle bus service will run between St-Laurent and Cyrville stations, and between Lees Station and Mackenzie King Bridge. After 11 pm, night service bus routes will run as scheduled.
This temporary closure is required for Stage 2 systems integration, in preparation for Line 1 service to be extended from Blair Station to Trim Station as part of the O-Train East extension.
For updates and trip planning assistance, visit octranspo.com or call 613-560-5000. You can also connect with OC Transpo on Facebook, X (formerly Twitter), and Instagram
——————-
Highway 417 Ramps at Pinecrest, Richmond to close until August
Expected until the end of August, the Highway 417 westbound on-ramp from southbound Pinecrest Road and the Highway 417 westbound off-ramp to Richmond Road will be closed and detours will be in place.
These closures are related to Stage 2 LRT roadwork. Signage will be in place, please plan ahead.
Motorists planning to access Highway 417 westbound from southbound Pinecrest Road will detour onto Baseline Road, westbound to Richmond Road, and then proceed northbound to Holly Acres Road and onto the 417.
Motorists travelling westbound on Highway 417 wishing to access Richmond Road or Bayshore Drive will be directed to exit the highway at Greenbank Road/Pinecrest Road.
Residents are encouraged to visit octranspo.com/alerts for details and detours related to your specific routes.
To learn more, go to: Notice of Long-term Ramp Closures: Highway 417 between Pinecrest Road and Richmond Road
——————–
Change of dates for re-opening of Corkstown Road to two way
Due to the weather last Thursday, paving was cancelled. Additionally, due to the rain on Thursday, the proof roll- which is a visual inspection of the subgrade under loading- failed which prevented paving on Friday. Re-work is ongoing to ensure the integrity of the granular base is sound and will the paved later this week.
——————–
Anticipated Impacts
Motorists should adhere to detours, traffic control signage, posted speed limits, allow for added travel time and use extra caution when moving through active construction corridors as traffic patterns change. Pedestrians and cyclists should use extra caution and adhere to posted signage when localized detours are in-place, to ensure safety. The safety of the public and workers is paramount, and we thank you for your patience during construction
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at octranspo.com/o-trainx.
For other accommodations, or questions, please contact:
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
Stage2@ottawa.ca
octranspo.com/o-trainx