The following is an update from Stage 2 with a 2025 Winter Lookahead for the work for the Richmond Road Revitalization Project, as well as the Overnight Work for Bay Ward for January 2025 to March 2025.
Stage 2 O-Train Light Rail Transit Project: 2025 Winter Lookahead
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, works on Richmond Road and Byron
Avenue between Cleary Avenue and McEwen Avenue will continue through 2025. Below is an overview of activities upcoming for the winter months of 2025. Please note that construction crews will be on holiday break from December 21 to January 5, inclusively. Construction operations during this time will be limited to winter maintenance and maintenance of temporary equipment including pumps.

What: Construction activities to advance the utilities installations
When: January through March 2025
Where: Richmond Road and Byron Avenue between McEwen Avenue and Cleary Avenue
Upcoming Construction Activities McEwen Avenue to New Orchard Avenue North:
• Utilities installation at Richmond Road and McEwen Avenue
• Electrical installations
New Orchard Avenue North to Woodroffe Avenue:
• Line drilling, rock breaking, and hauling material
• Utilities installations along Richmond Road
• Advancing station construction at New Orchard Station
Woodroffe Avenue to Cleary Avenue:
• Utilities installations and relocations at 75 Cleary
• Utilities installations along Richmond Road
• Advancing station construction at Sherbourne Station
Anticipated Impacts
Motorists and cyclists should heed all roadway signage in place through construction zones. Noise and vibration from crews and heavy equipment may be expected. All construction vehicles and equipment, working overnight will be equipped with broadband back-up alarms. Trucks use approved haul routes and workers and contractors park in designated parking areas.
Generators are required to run equipment in the tunnels and at site offices. When possible, generators are wrapped in noise barriers.
Site lighting is required to maintain safe working conditions for workers. The use of lights will be minimized where possible and special attention paid to ensure that it is not impacting nearby residences.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at octranspo.com/o-trainx and select updates for “Richmond Road Complete Streets”, “New Orchard Station” or “Sherbourne Station”. For other accommodations, or questions, please contact:
Stage 2 Team
Stage2@Ottawa.ca
Rail Construction Program,
City of Ottawa
octranspo.com/o-trainx
Overnight work in Ward 7 for the period of January 2025-March 2025
What: Night work is required along the LRT alignment from the LMSF to Kichi Zibi Station as work proceeds on bridges, structures, utilities, roads, stockpiles, berms, and the LRT guideway. Overnight activities may include excavation and hauling, backfilling, concrete pouring, utility installation, welding, grading, paving, fueling, equipment maintenance and servicing, site housekeeping and snow clearing operations.
*Unless otherwise notified, rock breaking, and vacuum truck excavation is NOT permitted overnight.
When: KEV anticipates that periodic night work will be required and ongoing throughout 2025. Night work will occur subject to a valid noise by-law exemption, in addition to daytime activities on weekdays and weekends. Night Work: Monday to Saturday 10:00 p.m. to 7:00 a.m. and 10:00 p.m. to 9:00 a.m. Sundays and Statutory holidays – will occur, as required, through March 2025.