- Moodie Station Area, Light Maintenance and Storage Facility (LMSF) and Highway 417 Interchange:
- LMSF retaining wall and block wall construction is ongoing.
- LMSF utilities relocation is ongoing.
- Pad and deck installations for the LMSF has started.
- Moodie Drive drilled shafts work is ongoing.
- Construction on the NW temporary ramp, with barrier installation at Moodie Drive continues.
- The SW ramp is closed as of April 1st.
- Holly Acres and Highway 417 Interchange
- SW ramp excavation and clearing is ongoing.
- Drainage work is ongoing.
- Girder is complete, deck installation ongoing.
- Pinecrest Station Area and Highway 417 Interchange
- NW ramp construction is in progress.
- Retaining wall construction is underway.
- Bridge formwork and abutments are ongoing.
- Drainage and stormwater work underway.
- Bridge deck formwork and rebar installation are ongoing.
- Rock breaking, line drilling, and excavation are underway.
- Lincoln Fields Flyover Rail Bridge (south of Lincoln Fields)
- Construction work of supporting structures is underway.
- Girder replacement, and diaphragms installation has started.
- Connaught Cut and Cover Tunnel and Queensview Station Area
- Watermain relocation has been connected on Connaught Avenue.
- Queensview Station sanitary line relocation work has started.
- Support of excavation and drilled shafts work is underway for the Connaught Tunnel.
- Lincoln Fields Station Area
- Carling Avenue watermain and storm water relocation is ongoing.
- Preparations for support of excavation for drilled shafts has started.
- Station pad installation is underway.
- Rock breaking is completed.
- Temporary traffic realignments are in place on Carling Avenue as work progresses.
- Stormwater installation is underway near Lawn Avenue Parkette and Lincoln Fields.
- Manhole relocations on Edgeworth is ongoing.
- Byron and Richmond Corridor (Byron Linear Park)
- Storm sewer, watermain and drainage work is ongoing with closures on Byron Avenue east of Woodroffe and on Richmond Road west of Hartleigh
- Cylinder piles are being drilled and rock breaking is underway onsite in support of the cut and cover tunnel excavation.
- Hydro-vac and hoe-ram excavations are underway on the Woodroffe watermain relocation. Lane reductions continue at Woodroffe/Richmond intersection.
- West Nepean Collector connection work is underway.
- Fencing and barrier installation and relocation is ongoing.
- Preparation for asphalt paving on Byron Avenue underway.