1- Completion of storm line excavation and installation in progress.
2- Selective demolition in the existing building on the third floor is completed, almost completed on the second floor and to continue on the first floor.
3- Building excavation on the new building has started.
4- Installation of formwork to start on January 21, 2019, weather permitted.
5- Major reinforcing steel delivery is expected this week in anticipation of starting the formwork.