Moodie Interchange, Moodie LRT Station and Moodie Light Maintenance and Storage Facility (LMSF):
- Structural steel erection of the Service and Inspection building is underway.
- Foundation construction for the Train Storage Shed and the Administrative Building is underway.
- Bridge deck construction of the future westbound on-ramp from northbound Moodie Drive is ongoing.
- Bridge deck construction of the future westbound 417 on-ramp from southbound Moodie Drive is ongoing.
- Bridge deck construction of the west portion of Moodie Drive over the LRT track (future southbound lanes) is ongoing.
Holly Acres and Highway 417 Interchange
- Construction work is ongoing on the toe wall on the new on-ramp.
- Paving and median work is underway.
Bayshore Station Area
- Bayshore bus loop construction is complete.
- Utilities relocation is ongoing.
Pinecrest Station Area
- Rock breaking, line drilling, and excavation are underway for the Pinecrest trench.
- Watermain relocation is underway.
- Grading work is occurring along westbound Highway 417.
- Bus-only ramp abutments and decking are ongoing.
Iris Station and Pinecrest Creek Area
- Pinecrest Creek realignment is complete.
- Preparation to remove the old culvert has begun.
- Support of excavation and excavation are complete for the Iris Street road-over-rail bridge.
- Culvert, and wall construction at the Pinecrest Stormwater Management Pond are underway.
Lincoln Fields Flyover Rail Bridge (south of Lincoln Fields)
- Work on columns and abutments for the new Woodroffe pedestrian bridge is ongoing.
- Split-structure deck panels and super structure construction continues.
Connaught Cut and Cover Tunnel and Queensview Station Area
- Watermain relocation in Connaught Park is ongoing.
- Queensview Station storm line relocation work is ongoing.
- Drilled shafts and concrete pouring for support of excavation are underway for the Connaught Tunnel along Queensview.
Lincoln Fields Station and Carling Avenue LRT Bridge
- Concrete pouring of the deck is ongoing.
- Structural steel and formwork installation is ongoing for the station.
- Retaining wall footings and wall work ongoing for the station.
- Watermain installation on Edgeworth is underway.
- At the north end of Lincoln Fields, bridge deck work crossing Richmond and at McEwen is complete. Excavation for the tunnel is ongoing.
- Station backfill work is ongoing.
Byron and Richmond Corridor (Byron Linear Park)
- Sanitary line relocation work at Hartleigh Avenue continues.
- Cylinder pile drilling, excavation and rock breaking are ongoing for tunnel work.
- Hydro connections to complete power supply connections for the project are ongoing.
- East of Woodroffe Avenue drilling, lagging and rock breaking are ongoing.
- New Orchard Station structure and rebar work are underway.
- Concrete pouring for the Parkway Tunnel walls is ongoing, requiring temporary closures along Byron Avenue until winter.
Rochester Field & Sir John A. Macdonald (SJAM) Parkway
- Parkway Tunnel drilling, support wall construction and excavation operations are ongoing.