Issued by the CEPEO (Conseil des écoles publique de l’Est de l’Ontario)
Look-ahead schedule for the next 4 weeks
Existing Grant building :
1- Level 3 – Mechanical & electrical rough-in
2- Level 2 – Drywall completed – started taping and prime walls
3- Ground floor- Drywall installation and taping.
4- Mechanical & electrical rough-in well under way on ground floor and basement
New section in construction :
5- Interior and soffit framing of the gymnasium in progress.
6- Masonry on the exterior wall at the gymnasium in progress.
7- Mechanical and electrical rough framing at the gymnasium in progress.
8- Underground mechanical and electrical is completed at the daycare.
9- Concrete slab scheduled to be poured on July 11, 2019 at the daycare.