Look-ahead schedule for the next 4 weeks
Existing Grant building :
1- Metal stud framing installation.
2- Start installation of drywall.
3- New window installation in progress.
4- Mechanical & electrical rough-in well under way.
New section in construction :
5- Gymnasium structural steel to complete.
6- Slab on grade for the gymnasium completed.
7- Start exterior wall at the gymnasium.
8- Underground mechanical and electrical rough-ins to start at the daycare.
9- Steel structure in progress at the daycare.