Look-ahead schedule for the next 4 weeks :
Existing Grant building :
1- Level 3 – Drywall : started taping and prime walls.
2- Level 2 – grid /ceiling tiles installation and flooring
3- Ground floor- Drywall : Taping, roofing and electrical.
4- Mechanical & electrical rough-in – continues in the basement
5- Attic space – Mechanical and electrical rough-in and roof work.
New section in construction :
6- Gym : Drywall – Taping, Curtain wall installation.
7- Mechanical and electrical rough framing at the gymnasium continues.
8- Daycare : Drywall installation and mechanical and electrical rough-ins.
9- Daycare : Curtain wall completed.
10- Link : Drywall installation, Mechanical & electrical rough-in.
11- Exterior work : Started excavation of the new parking areas. Prepare for curbs and sidewalks.