- Light Maintenance and Storage Facility (LMSF) retaining wall construction is ongoing.
- LMSF utilities relocation is ongoing.
- Precast panels for the LMSF has started.
- Moodie Drive drilled shafts work is ongoing.
- North West temporary ramp has flipped to new ramp.
- Retaining wall excavation is underway.
- Bridge preparation has started with deep foundation work.
- The westbound on-ramp from northbound Moodie Drive is closed until December 2021.