Calendar of Events
S Sun
M Mon
T Tue
W Wed
T Thu
F Fri
S Sat
12 events,
Westbound Pinecrest Road Off-ramp Closure
The Stage 2 LRT team will undertake significant construction activities on the O-Train West extension in preparation for future tracks and stations. Starting overnight on November 1, Highway 417 westbound off-ramp…
Nightwork Richmond – Cleary – Sir John A Macdonald (SJAM) Parkway
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, construction activities in the Richmond-Cleary-Sir John A Macdonald (SJAM) Parkway area are increasing. Time sensitive work to relocate a…
Sidewalks on Carling Ave at Lincoln Fields Station
When will the Carling sidewalk between Edgeworth and the Rexall be back to normal? The sidewalk on Carling will return to service once the work excavating below Carling Avenue for…
Notice of Night Work – Queensview Drive along Highway 417
Night work is required from the area of Queensview Drive along Highway 417, near the Pinecrest Road Interchange. Overnight activities will include drilling, excavation and hauling. Beginning February 22 through…
LRT2 Prep for permanent transitway closure to buses between Tunney’s Pasture & Dominion Stations
This year, the Stage 2 LRT Project will meet another major milestone with the closure of the Transitway to allow for guideway work to commence. Beginning on June 26, 2022…
90-Day Lookahead – Byron Avenue and Byron Linear Park
April through June 2022 OVERVIEW The O-Train West Extension is one of the three major extensions to Ottawa’s Light Rail Transit Project. The extension will add over 15 km of…
90-Day Lookahead – Lincoln Fields
April through June 2022 OVERVIEW The O-Train West Extension is one of the three major extensions to Ottawa’s Light Rail Transit Project. The extension will add over 15 km of…
90-Day Lookahead – Ambleside Detour
April through June 2022 OVERVIEW The O-Train West Extension is one of the three major extensions to Ottawa’s Light Rail Transit Project. The extension will add over 15 km of…
90-Day Lookahead – McEwen Avenue and Edgeworth Avenue
April through June 2022 OVERVIEW The O-Train West Extension is one of the three major extensions to Ottawa’s Light Rail Transit Project. The extension will add over 15 km of…
Road closure of Ashley St.
This notice is to advise that, as part of the Stage 2 O-Train Light Rail Transit (LRT) project, Ashley Street will close to traffic. Please note, access to 1070 Morrison…
Night Work Summary – Week of April 25, 2022
Street sweeping will take place across the West Extension project area, as needed Dewatering operations, and maintenance of heaters and pumps will be ongoing in many areas throughout spring, including…
Notice of Night Work: Pinecrest to Holly Acres
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, crews and equipment will be working overnight along the Transitway between Pinecrest Interchange and Bayshore Shopping Centre to…
13 events,
Night Work Summary Week of May 2
Street sweeping will take place across the West Extension project area, as needed Dewatering operations, and maintenance of heaters and pumps will be ongoing in many areas throughout spring, including…
LRT Weekly Night Work Summary – Week of May 2
Street sweeping will take place across the West Extension project area, as needed Dewatering operations, and maintenance of heaters and pumps will be ongoing in many areas throughout spring, including…
13 events,
13 events,
13 events,
13 events,
13 events,
13 events,
11 events,
11 events,
11 events,
11 events,
11 events,
11 events,
11 events,
12 events,
Night Work Summary – Week of May 16th
Street sweeping will take place across the West Extension project area, as needed Dewatering operations and maintenance of pumps will be ongoing in many areas throughout spring, including on weekends…
12 events,
12 events,
12 events,
12 events,
12 events,
12 events,
11 events,
11 events,
11 events,
11 events,
11 events,
11 events,
11 events,
11 events,
11 events,
10 events,
10 events,
10 events,
10 events,




90-Day Lookahead – Lincoln Fields

90-Day Lookahead – Ambleside Detour


Road closure of Ashley St.






90-Day Lookahead – Lincoln Fields

90-Day Lookahead – Ambleside Detour


Road closure of Ashley St.

Night Work Summary Week of May 2






90-Day Lookahead – Lincoln Fields

90-Day Lookahead – Ambleside Detour


Road closure of Ashley St.

Night Work Summary Week of May 2






90-Day Lookahead – Lincoln Fields

90-Day Lookahead – Ambleside Detour


Road closure of Ashley St.

Night Work Summary Week of May 2






90-Day Lookahead – Lincoln Fields

90-Day Lookahead – Ambleside Detour


Road closure of Ashley St.

Night Work Summary Week of May 2






90-Day Lookahead – Lincoln Fields

90-Day Lookahead – Ambleside Detour


Road closure of Ashley St.

Night Work Summary Week of May 2






90-Day Lookahead – Lincoln Fields

90-Day Lookahead – Ambleside Detour


Road closure of Ashley St.

Night Work Summary Week of May 2






90-Day Lookahead – Lincoln Fields

90-Day Lookahead – Ambleside Detour


Road closure of Ashley St.


Night Work Summary Week of May 2





90-Day Lookahead – Lincoln Fields

90-Day Lookahead – Ambleside Detour


Road closure of Ashley St.





90-Day Lookahead – Lincoln Fields

90-Day Lookahead – Ambleside Detour


Road closure of Ashley St.
