O-Train – Ward 7
- Moodie Station Area and Light Maintenance and Storage Facility (LMSF):
- LMSF retaining wall and block wall construction is underway.
- LMSF sanitary and watermain work is underway.
- Moodie Drive drilled shafts and soldier pile work is underway with abutments to follow.
- NW temporary ramp construction at Moodie Drive is ongoing.
- Holly Acres and Highway 417 Interchange
- Electrical duct bank work is underway.
- Abutment construction is ongoing.
- Pier cap installation is ongoing.
- Pinecrest Station Area
- Northwest quadrant support of excavation is in progress.
- Retaining wall construction for new NW ramp is underway.
- Bridge formwork and abutments are ongoing.
- Excavation of NE section has started.
- Lincoln Fields Flyover Rail Bridge (south of Lincoln Fields)
- Supporting structures construction work is underway.
- Retaining wall construction is ongoing.
- Backfilling is ongoing.
- Connaught Cut and Cover Tunnel
- Watermain relocation is underway on Connaught Avenue.
- Queensview Station area preparation underway for utilities relocation and excavation.
- Lincoln Fields Station Area
- Carling Avenue watermain relocation is ongoing.
- Station excavation is underway.
- Rock breaking is ongoing for utilities work.
- Temporary traffic realignments are in place on Carling Avenue as work progresses.
- Utility work is ongoing on the north side of Lincoln Fields Station.
- Pathway detour is in place.
- Stormwater relocation has begun near Lawn Ave Parkette and Lincoln Fields.
- Byron and Richmond Corridor (Byron Linear Park)
- Underground utility relocation is ongoing on Byron Avenue.
- Utilities relocation work on Richmond Road and McEwen Avenue is ongoing.
- Cylinder piles are being drilled to support cut and cover excavation.
- Road closures and lane reductions are ongoing for utilities work.