- Byron between Sherbourne and Lockart will be opened to traffic end of day today April 16th.
- Byron between Woodroffe and Lockart:
- Utilities day shift activities are completed so the road will be reopened to traffic during day shift of April 16th.
- Utilities night shift activities at Woodroffe will continue and some TCPs do require the road to be closed.
Paving activities on Byron (east and west of Woodroffe) will be happening again next week.