Limited access to Starflower Lane between Croydon Avenue and Assaly Road
Hydro Ottawa will be working on Starflower Lane between Croydon Avenue and Assaly Road installing undergound civil structures to allow for the installation of few underground electrical cables that will service the new Queensview and Bayshore LRT Stations. Hydro Ottawa will have on-going construction in the area weekdays between 7 :00am and 5 :00pm.
Starflower Lane will have limited access from both Assaly Road and Croydon Avenue and Traffic Control Personnel will be on site during working hours to assist vehicle traffic entering and exiting Starflower Lane.
No planned power interruptions are expected to occur as a result of this project.
* Affected Streets: Starflower Lane between Croydon Avenue, and Assaly Road
* Project estimated start date: Monday May 16, 2022
* Project estimated completion date: Friday May 27, 2022
* Hydro Ottawa Civil Contractor : Bradley Kelly Construction