At Friday’s Special Finance and Economic Development Committee, Transit Services provided a detailed update on its Stage 2 construction activities. Work continues on the O-Train network, extending it farther south, east and west.
In the south, work is progressing at the Walkley maintenance and storage facility and on multiple rail bridges and guideways. Station construction has begun at all sites, and preliminary vehicle tests are underway on a test track.
In the east, road work and utility relocation are ongoing on Highway 174, and work has begun on stations and tracks. The bridge from Blair Road to the Highway 174 median is nearly complete, and the overpasses at the Montreal Road highway interchange are progressing well. Track installation has begun between Montréal and Jeanne d’Arc stations.
In the west, work is ongoing at the Moodie light maintenance and storage facility, Pinecrest Station, Queensview Station, Iris Road and Pinecrest Creek, Algonquin Station, Lincoln Fields Station, and Byron Linear Park excavation. Tunnel construction is progressing along the Sir John A. Macdonald Parkway. Work is progressing well at the highway interchanges at Pinecrest and Holly Acres roads.