Moodie Station Area and LMSF |
- Moodie interchange excavation and embankment
- Moodie drainage
- Moodie Station excavation
- Transitway Moodie to Holly Acres – drainage & excavation
|
Holly Acres |
- Road work
- Drainage installation
|
Bayshore Station Area |
|
Pinecrest Station Area |
- Hauling
- Roadway work
- Utility work
|
Split Structure + Ped Bridge + south of Carling Avenue |
- Roadway work on Carling at Lincoln Fields
- Retaining wall work on Carling Ave
- Flyover/Split Structure: backfill
|
Connaught Park + Connaught Avenue |
|
Queensview Station Area |
|
Lincoln Fields – Richmond to Carling |
- Station backfill and stockpiling
- Excavation
|
Byron and Richmond Corridor – West of Woodroffe |
- Evening work until 10:00 p.m. on Richmond Road, west of Woodroffe, at McEwen Avenue for drilling
|
Byron and Richmond Corridor – East of Woodroffe |
|