Night Work Summary Nov 8 to 14
November 9, 2021 @ 8:00 am - 5:00 pm
General Area |
Work summary |
Moodie Station Area and LMSF |
- Moodie interchange excavation and embankment
- Moodie drainage
- Moodie Station excavation
- Transitway Moodie to Holly Acres – drainage & excavation
- Corkstown Road construction
|
Holly Acres |
- Road work
- Drainage and electrical installation
- Excavation
|
Bayshore Station Area |
|
Pinecrest Station Area |
- Hauling
- Roadway work
- Utility work
|
Split Structure + Ped Bridge + south of Carling |
- Roadway work on Carling at Lincoln Fields
- Retaining wall work on Carling Ave
- Flyover/Split Structure: backfill using dump trucks and excavators
- Loading materials for Station backfill using dump trucks and excavators
- Transitway – pad construction
|
Connaught Park + Connaught Ave area |
|
Queensview Station Area |
|
Lincoln Fields – Richmond to Carling |
- Station backfill and stockpiling, with dump trucks and excavators
- Excavation
- Carling Avenue – Detour and drainage construction
|
Byron and Richmond Corridor – West of Woodroffe |
|
Byron and Richmond Corridor – East of Woodroffe |
|