Maison de la Francophonie – Construction Activities – July 2019
Issued by the CEPEO (Conseil des écoles publique de l’Est de l’Ontario) Look-ahead schedule for the next 4 weeks Existing Grant building : 1- Level 3 – Mechanical & electrical rough-in 2- Level 2 – Drywall completed – started taping and prime walls 3- Ground floor- Drywall installation and taping. 4- Mechanical & electrical rough-in…