LRT Stage 2: What is a Design Build?
As a Design-Build the LRT Stage 2 project unfolds differently than all other typical city projects. Design work and construction activities both advance in tandem and many detailed designs (such…
As a Design-Build the LRT Stage 2 project unfolds differently than all other typical city projects. Design work and construction activities both advance in tandem and many detailed designs (such…
On Monday, March 2nd, the City of Ottawa released the procurement documents for the Stage 2 Light-Rail Transit Trillium Line to the public. The documents show that TransitNEXT received the…
Update August 2020 – Status of the Hydro One cable relocation project in Lincoln Fields In February, Hydro One delivered notices to residents living on Rosewood Ave and Georgina Dr.…
Description: On behalf of Bell and Rogers, KEV is relocating existing underground Bell and Rogers ductbanks on Carling Ave. The ductbanks are to be relocated South and out of the…
Overall Preparatory activities (borehole drilling, site office mobilization, pre-construction surveys, site preparations and tree clearing, etc.) are currently underway on each O-Train extension. O-Train Confederation Line West Extension • Vegetation…
On Thursday, January 23, 2020, the Director of Rail Construction Program released the memo related to the Stage 2 Project procurement evaluations and three related appendices. I have included them…
Our office received news this week from the LRT Stage 2 Team. The contractor has informed the City that they have updated their design of the Lincoln Fields bus loop…
Overall Preparatory activities (borehole drilling, site office mobilization, pre-construction surveys, site preparations and tree clearing, etc.) are currently underway on each O-Train extension. O-Train Confederation Line West Extension Tree and…
The following questions were submitted by residents of Bay Ward to the Stage 2 Team. Q1: When will the LRT Trenching start and Cover be completed between Cleary and New…
Please be advised that the NCC has provided approval to continue with the removals of trees within Lincoln Fields, primarily the crab-apple orchard north of Lincoln Fields Station. The consortium…