Update on the Connaught Berm Design Proposal
To view a high resolution of the draft berm design: Connaught Berm Draft Design Proposal KEV has indicated they are no longer going to pursue enhanced berming through Connaught Park…
To view a high resolution of the draft berm design: Connaught Berm Draft Design Proposal KEV has indicated they are no longer going to pursue enhanced berming through Connaught Park…
This notice is to advise that, as part of the Stage 2 O-Train Light Rail Transit (LRT) project, Byron Linear Park between Redwood Avenue and Richardson Avenue will be closed…
Overall The City of Ottawa’s Rail Construction Program is closely monitoring the COVID-19 situation and is in contact with the constructors about adhering to guidance provided by Ottawa Public Health…
July 2020 This notice is to advise that, crews and equipment will be relocating utilities, and doing roadwork along Richmond Road and Byron Avenue in preparation for cut and cover…
The picture below illustrates the approximate position of the LRT bridge that will go over Holly Acres.
We received notice from the City’s construction team that KEV unexpectedly found some rock in the area that they are digging for the sewer relocation, and as a result are…
Beginning Monday, July 13th Hydro Ottawa will begin construction of their duct banks on the north side of Richmond Road by McEwen Avenue. The works are expected to take approximately…
Please note, KEV is advising of the remaining elements of their Carling Detour works (map shown below) that they propose to undertake at night between July 17th to July 31st.…
As part of our commitment to keep you informed about planned work project scheduled to take place in your ward, I would like inform you about upcoming planned work that…
The Stage 2 Light Rail Transit project will extend the O-Train farther south, east, and west, bringing 77% of residents within five kilometres of rail. Construction is underway with design…