I wanted to inform you that we will be closing Carling Avenue between Herzberg Road and Moodie Drive for one weekend to construct the sanitary crossing as part of the North Kanata Trunk Sewer project. Additional information regarding the crossing can be found below.
When: September 13, 2019 7PM to September 16, 2019 6AM
What: The work includes the installation of 1200D sanitary sewer across Carling Avenue.
Where: Carling Avenue will be closed between Herzberg Road and Moodie Drive.
Traffic Impacts: Carling Avenue will be closed between Moodie Drive and Herzberg Road. PVMS boards will be installed 10 days in advance of the closure. During the road closure, a detour will be implemented. A hard surface for pedestrians and cyclists will be maintained on Carling Avenue throughout the construction zone. For safety reasons, cyclists may be asked to dismount and walk in areas close to construction. Paving operations on Carling Ave will be completed off peak hours on the Monday (16th) following the closure.
NOTE: There will be hard closure from Herzberg to Burke only, local traffic can still access businesses along Carling like 19th Tee.