On behalf of Bell and Rogers, KEV is relocating existing underground Bell and Rogers ductbanks on Carling Ave. The ductbanks are to be relocated South and out of the existing road corridor to allow for the construction of the new overpass over the proposed LRT tracks, South of Lincoln Fields Station.
Proposed construction Dates:
- Estimated civil works: February 10, 2020 to April 15, 2020
- Estimated cabling works: April 27, 2020 to April 26, 2021
KEV: Kiewith/Eurovia/Vinci Ottawa Partnership